The Union Minister of New and Renewable Energy, Dr.
Farooq Abdulla, informed the Rajya Sabha in a written reply that under
Jawaharlal Nehru National Solar Mission (JNNSM) India is to create a
capacity for generation of 1100 MW of grid connected solar power by 2013
and 20,000 MW by 2022. The overall investment may be approximately $
40 billion for 20,000 MW of solar power projects.
The current installed generation capacity of India is 205340.26 MW
which includes 24832.68 MW generated through renewable energy sources.
JNNSM aims at achieving 20,000 MW by 2022 thereby it will then
constitute one-tenth of India’s current installed power base. The total
installed capacity in the country is likely to be more than 400 GW by
2022. Installed solar capacity then would be one-twentieth of the then
India’s total installed capacity. The share of renewable and
particularly solar in country’s energy mix would keep increasing and
would certainly help in limiting reliance on coal and easing the power
deficit.
The Minister further said that against a target of 1100 MW of grid
connected solar power by 2013, 1030 MW of solar power projects have been
commissioned and connected to grid, these are under both Central and
State initiatives.
Issues like upgradation of transmission network, availability of
unallocated power for bundling, delay in payment by DISCOMS, weak State
Nodal Agencies are being focused on. A transmission network upgradation
plan has been prepared by Power Grid Corporation of India Limited.
Ministry of Power has been requested for giving unallocated power.
Payments from DISCOMS are being monitored continuously and States are
being requested to upgrade Nodal Agencies.